The Disneyland Resort Paris did not enjoy a pleasant birth. Following on from the success of the Disneyland theme park in Anaheim, plans to build a European version first started around 1975, nine years after Walt Disney died. Initially Britain, Italy, Spain and France were all considered as possible locations, though Britain and Italy were quickly dropped from the list of potential sites because they both lacked a suitably large expanse of flat land. The WDC were determined not to make the same mistake as in Anaheim, where speculators bought the land surrounding the first Park and preceded to cash in on its success. The most likely site was felt to be in the Alicante area of Spain, which had a similar climate to that in Florida for a large part of the year. However, the area was also beset by the notorious Mistral winds.
Eventually the French location won, and a site was duly investigated at Marne-la-Vallee, partly because of its close proximity to Paris, and also its central position within Europe, a factor thought to be crucial to the Park's future success if it was to attract sufficient visitors. The proposed location put the park within 4 hours drive for around 68 million people, and 2 hours flight for a further 300 million or so. Michael Eisner signed the first letter of agreement with the French Government in December 1985, and started to draw up the financial contracts during the following spring. Robert Fitzpatrick, a key organiser of the 1984 Los Angeles Olympics, was appointed as the Euro Disney President, and the park slowly started to take shape, with construction starting on the 2,000-hectare site - about one fifth the size of Paris - in August 1988.
Meanwhile, the Government's compulsory purchasing of the farmland in Marne la Valee had not endowed the local agrarians with unalloyed joy and they, together with the French Cultural Elite, waged a war of words against the new theme park, its owners and Americans in general. Nevertheless, the French Government pressed ahead and Euro Disney first opened to employees, for testing, during late March 1992, during which time the main sponsors and their families were invited to visit the new park. The formal press preview day was held on April 11th 1992, and the park finally opened to visitors on April 12th 1992.
The first phase of development (the theme park, hotel complex and golf course) had gone massively over budget, and had eventually cost 22 billion French Francs to complete. Over the next few months attendance figures failed to improve much, and by May the park was only attracting something like 25,000 visitors a day, instead of the predicted 60,000. Combined with the realisation that only 3 in every 10 visitors were native French, the Euro Disney company stock price started a rapid downward spiral, losing almost four fifths of its value. Combined with incredibly optimistic over-pricing of hotel rooms, meals and merchandise, the Park was headed for a disaster.
Crisis looms...
Rescue ...Matters came to a head during March 1994 when Team Disney presented the 38 backing Banks with an ultimatum: The WDC would provide sufficient capital investment for the park to continue to operate until the end of the month, but would close the park, and walk away from the entire European venture, unless the banks agreed to restructure the $1bn debt that the park's construction and operation had run up, The bankers realised that, to be left with a bankrupt theme park and a massive expanse of virtually worthless real estate would not be in their best interests and, since most of them had been writing off loans to third world countries for some time, wondered whether their desks would still be there the following day. Euro Disney then forced the banks’ hands by calling the annual stockholder meeting for March 15th. Faced with no alternative other than to announce to the stockholders that the park was about to close the banks started looking for ways to refinance and restructure the massive debts. Cleverly increasing the pressure on the banks, Michael Eisner, Disney's CEO, went public shortly before the stock-holder meeting and announced that Disney were planning to pull the plug on the venture at the end of March 1994 unless the banks were prepared to restructure the loans. On March 14th, just prior to the annual meeting the banks capitulated, and agreed to Disney's demands, effectively writing off virtually all of the next two years worth of interest payments, and agreed a three year postponement of further loan repayments. In return the Walt Disney Company wrote off $210m in unpaid bills for services, and paid $540m for a 49% stake in the estimated value of the park, as well as restructuring its own loan arrangements for the $210m worth of rides at the new park. In addition, a Saudi Prince - Prince Alwaleed - invested heavily in the park, purchasing 23% of the stock. The tide turns... By August of 1994 the Park was slowly starting to find its feet, and all of the Park's hotels were fully booked during the peak holiday season. In October 1994 the Park's name was officially changed from Euro Disney to "Disneyland Paris", in order to strengthen the link between the Park and the romantic city of Paris, and to disassociate itself from the poor reputation that had become linked with the name "Euro Disney". At the same time, prices for food in the Disneyland cafes were substantially reduced, the French Franc began a slide against Sterling and hotel and package prices were reduced. These actions were to effectively double the number of visitors from the UK and other regions of Europe, but not until 1995, owing to the built in 'lag' caused by British holiday planning patterns. The end of year figures for 1994 showed encouraging signs as the previous year's £650 million loss was reduced to around £200 million, despite a 10% fall in attendance caused by bad publicity over the earlier financial problems. By the end of March 1995 top Walt Disney executives were predicting that Disneyland Paris would break-even by the end of 1995. Helped by the opening of Space Mountain on June 1st 1995, in August that year Disneyland Paris and the Euro Disney resort complex announced a £22m profit, followed by the first annual operating profit announced in November 1995. The Gaumant conemas opened in the Disney Village in 1996 and Planet Hollywood opened in 1997. During that two years, rates across the resort remained stable, groundbreaking for the ambitious Val d’ Europe project commenced and the Park itself acquired new attractions in the shape of The Storybook water ride and Casey Jr. mini coaster. 1998 saw the World Cup held in France, which dented attendance figures, but still 12.7 million visited the park. Theme park spending per guest increased markedly and France, Benelux and the UK respectively accounted for 70% of the Park’s guests. A second State of the Art convention centre was opened at the Newport Bay Hotel, the Park transplanted the WDW ‘Tinkerbell’s fantasy in the Sky’ from WDW to DLP and the Gaumont Cinema chain opened an extra 16 screens. At this time, the interest rate payments that the banks had foregone in 1994 and the royalty’s payments to the WDC became due in stages, so - despite increased revenues - the overall profits for the Park were reduced. In 1999, Disney Village continued its aggressive expansion phase with the opening of the Rainforest and MacDonald’s cafes and the building of the Walt Disney Studios was commenced in earnest. The Park saw ‘Honey, I shrunk the Audience’ open, having been imported from WDW’s Epcot Centre. To deal with the different holiday patterns in Europe, weekends became a focus for packages and the Park expanded the seasonal entertainment specials, including Halloween, Guy Fawkes (the French love that one!) and Christmas, which had the combined effect of filling the hotels at weekends and up to 82% during the weekdays. On the 26th December, 1999, however, a monster storm devastated the park, damaging and destroying much of the Camp Davy Crockett, the newly launched Crescend’O tented show in Disney Village and closing the park for several hours, a disaster given the peak holiday period. Undeterred, 2000 saw the introduction of FastPass, a re-engineering of Indiana Jones (it goes backwards, now!) the presentation of Tarzan on the Chaparral theatre stage and the opening of a kids’ play area, Pirate Beach in Adventureland. The ill-fated Agrabah cafe was also opened, shortly before being gutted by fire. Nonetheless, France and the UK now accounted for over 55% of visitors and Germany was an increasing contributor. In 2001, hotel occupancy increased to over 86% - an astonishing figure, well in excess of Florida's park - and the Park welcomed its millionth visitor. Only Toon circus was new in entertainment terms, although the phenomenally successful Mulan continued to run in Videopolis but Jay Rasulo was able to announce that the Walt Disney Studios would be opened on 16th March 2002. The symbolism of opening the new Park, ahead of schedule before the tenth anniversary of the opening of Euro Disney was potent, and a marker of maturity for the company. Just when the future held much promise, however, fate was to deal the worst blow. In the summer of 2001, alerted by French Intelligence of a possible terrorist strike against American interests, security increased dramatically at the Park. September 11th brought tragic confirmation of that warning and damaged the package holiday, Airline and Travel industries substantially. In 2003, Jay Rasulo - who had opened the new Studios, was promoted to greater things within the company, and a new boy - Andre Lacroix, at 33 a young man - took over. His first public statements laid bare the worrying financial position of the company. The ongoing problems in tourism, the French labour difficulties and the costs incurred in building the new park which had failed to realise its potential had all combined to damage the profitability of the resort, which had incurred its first serious loss in several years. At the time of writing, Andre has implemented the "Need Magic?" campaign, which - with short but pithy slots on all TV channels in Europe - is firmly aimed at the first time visitor. Only time will tell if this strategy will succeed. An aerial view durning construction of Big Thunder Mountain. The actual ride is quite different from it’s cousins in the USA and Japan as it uses a water splash and underwater access routes. A painting which hangs in the Disneyland offering an artist's impression of the view down Main Street from the Hotel. In fact, because of the Railway, very little of Main Street can be seen from the Hotel. An aerial view of the contruction phase of Adventure Island and the Pirate ship. As can be seen, the lakes and hills in the park are all created features. Note the use of 'berms' - high banks of earth and trees - that is standard in all Disney Parks to prevent other areas being seen from witin the park. Our Holidays A Brief History